The three-point estimating technique has its problems. For one, it is time consuming; performing the
Title
calculations can take a long time, even when a computer is used, especially for a large project. Also, it is
laborious; performing the calculations requires considerable thinking and searching for reliable information.
Lastly, not too many people understand the reasons for taking this approach; its underpinnings are probability
and bell curve analysis, which can be intimidating and too academic for some people.
-----------
How to Reevaluate an Estimate
Sometimes you might feel uncomfortable with an estimate. Perhaps you suspect it is unrealistic. Perhaps
you think the reasoning behind it is faulty. Perhaps you do not trust the people making the estimate.
Whatever the reason, you can take several actions to validate the estimate.
You can check the historical records of other projects that dealt with similar work. Sometimes, however,
such data are either difficult to obtain or unavailable.
You can seek a second opinion. It might mean going to someone on another project where similar work was
performed. It might mean going to an outside expert or organization for an evaluation.
You can benchmark one or more tasks. It may mean comparing the estimates with similar ongoing or
completed projects, either inside or outside your company.
You can apply the Delphi approach. Simply identify a number of people to provide input on an estimate.
Then make the adjustment and resubmit the estimate to them for further adjustment. The adjustment ends
once you gain concurrence or are comfortable with the result.
Finally, you can conduct peer reviews. Once all the estimates are complete, you can assemble everyone in a
room to discuss the estimate for each task. Assumptions and issues may arise that will call into question the
validity of some estimates. New estimates can then be developed.

The technique, however, does offer four benefits. It forces people to think seriously about the time to
complete a task; the three variables require looking at as many parameters as possible to calculate a realistic
estimate. The estimate is more reliable than other estimating techniques; it accounts for many parameters to
compensate for being too optimistic or pessimistic. It improves communication; discussion over the
parameters that relate to each variable forces people to communicate to come to a conclusion. It identifies
issues and assumptions early. When calculating each variable, people must identify issues and assumptions.
To ignore issues and assumptions adds to the cost of addressing them later in the project cycle.
What Happens When No One Wants to Give the Project Manager an Estimate?
Project managers often lack formal authority over the people on their teams. This is especially the case in a
matrix environment, where people report to a functional manager and may support several projects
simultaneously.
Sometimes project managers just do not get cooperation from team members. The team members may fear
commiting themselves, hate to wrestle with unknowns or ambiguities, or just not like the project manager.
What, then, is a project manager to do?
Project managers have several options:
1. They can document the refusal to cooperate in a memo and address it to the functional manager.
This takes advantage of formal authority to get the estimate.
2. They can hold a team meeting, where everyone can discuss and share their estimates in the
presence of other team members. This takes advantage of peer pressure to get the estimate.
3. They can solicit input from other people. Then they present the estimate to the uncooperative team
member and formally request his or her feedback. This takes advantage of professional pride.
4. They can make the estimate themselves and inform the person in a memo that unless there is
acceptance by a certain date, the accuracy of the estimate will be assumed. This takes advantage of
time pressure.

Of the four estimating techniques, Perry elects the three-point estimating technique. He believes that it will
provide more-reliable estimates and also offer many other benefits. So, using the three-point estimating
technique requires Perry to keep in mind the following points.
1. He must get input estimates from the people who will do the actual work. He appreciates their
knowledge of what is required to complete the work. He also knows that getting their input will
encourage commitment to their assigned tasks. It is one thing to follow someone™s dictate of the hours
to do the work; it is another when he does the estimate himself.
2. He must look at the historical records of other projects. Rather than apply the estimating technique
for all tasks, he may uncover some reliable estimates that can be reused for similar tasks. He is cautious
enough to realize that circumstances are not always exactly the same from one project to another.
Consequently, the reusable estimate may require revision. Also, he reminds himself that it is still a good
idea to get input from people who will do the work.
3. He must identify and document the assumptions and parameters used to derive the estimates. Doing
this is important for two reasons. First, he and others will better understand the rationale behind the
estimates. Second, he can also determine what has changed since making the estimate and make
revisions accordingly.
4. He must maintain consistency in the estimating process. He avoids using the three-point estimate
technique for some tasks and not for others. Otherwise, he will mix “apples with oranges,” with some
estimates being realistic, optimistic, or pessimistic. A lack of discipline in this regard can result in an
unrealistic schedule.
5. He must make the estimates public. After getting feedback, he will publish the estimates. He does
not hide the estimates, as though they were his personal golf scores or bowling averages. By publishing
the estimates, Perry knows that people will feel a subtle pressure to use them.
6. He must understand that the estimates are approximations, not accuracies. Circumstances change
that make estimates irrelevant. That requires reestimating during the project to increase the reliability
and validity of the overall estimate. Ideally, an estimate has the highest confidence level, which
becomes more possible as a project progresses through its cycle.

Factors to Consider in Drawing Up Estimates
Estimators consider many factors when performing their calculations. These include:
• Availability of nonlabor support
• Clarity and definitiveness of scope
• Complexity of the work
• Degree of available information to estimate
• Degree of uncertainty or risk in achieving the outcome
• Experience, knowledge, and expertise of the team members
• Financial constraints on the project
• History of similar work performed
• Legal constraints on the project
• Location of team members working on the task
• Number of people assigned to the task
• Number of potential interruptions
• Priority of the task
• Productivity of team members
• Project size
• Standardization of processes related to the task
• Structure versus unstructured nature of the work to be performed
• Whether the completion date of the task is dictated
When estimating, Perry will consider Parkinson™s law. He knows that too much available time to perform a
task is almost as troublesome as too little. Parkinson™s law, of course, says that work expands to fill the time
available. In other words, if given ten hours to complete a task when it ordinarily takes five hours, people will
take ten hours. So Perry treats Parkinson™s law seriously.
Perry is now ready for the next big planning action: developing a schedule.

Questions for Getting Started
1. Did you identify all the work package items in the work breakdown structure?
2. Did you select the most appropriate estimating technique? What are the reasons for your choice?
3. With at least the core team members, did you get time estimates for the tasks they are responsible
for completing?
4. If you meet resistance, how do you plan to overcome it?
5. If necessary, how will you reevaluate estimates? Review historical records? Apply the Delphi
approach?


Previous Table of Contents Next




Products | Contact Us | About Us | Privacy | Ad Info | Home

Use of this site is subject to certain Terms & Conditions, Copyright © 1996-2000 EarthWeb Inc. All rights
reserved. Reproduction whole or in part in any form or medium without express written permission of
EarthWeb is prohibited. Read EarthWeb's privacy statement.
Project Management Practitioner's Handbook
by Ralph L. Kleim and Irwin S. Ludin
AMACOM Books
ISBN: 0814403964 Pub Date: 01/01/98

Search this book:
Search Tips

Advanced Search


Previous Table of Contents Next



Title
Chapter 8
Schedule Development and the Network Diagram
With the statement of work and the work estimates completed, Perry is now ready to do some scheduling. In
-----------
so doing, he will juggle six factors: scope, time, duration, tasks, logic, and resources. The scope is described
in the SOW. Time is the hour estimate to complete each task”in other words, the estimates. Duration is the
hour figure converted to flow time for completing each task and, consequently, the entire project. Tasks are
the entries in the WBS. Logic is the sequence of tasks. And resources are the labor and nonlabor investments
assigned to each task. But all of this will become clearer as we explain more about scheduling.

What Scheduling Is
Scheduling entails making a logical sequence of tasks and then calculating start and stop dates for each task.
The results are displayed as a diagram.
A schedule is only useful if people are willing to commit themselves to maintaining it. Therefore, Perry sits
down with his core team and determines the logical sequence of tasks. He has everyone look at the big
picture, tying together all the tasks. They use this perspective to draw a network diagram, like the one in
Exhibit 8-1. The network diagram displays the logical relationships between the tasks.
Network diagramming may initially seem complex, especially if you™ve not had previous experience drawing
flowcharts. The advantages, however, are great. By constructing the diagram, you focus on the project goal
and discover the appropriate approach. Difficult issues become apparent, so the effort and expense of dealing
with them later is avoided. In addition, the diagram enables easier tracking of performance because it is based
on the work-package level items in the WBS. Finally, making forecasts and “what-if” scenarios is easier.
Warning Signs of Bad Scheduling Practices
Bad scheduling practices can tarnish the credibility of a schedule. Watch for these two common indicators
of bad scheduling:
• Warning Sign Number 1: Sometimes people are unsure of the future, so rather than calculate an end
date for a task, they write “TBD,” or “to be determined.” It not only represents unclear and
incomplete thinking but also opens the opportunity for guesswork and poor oversight of tasks.
• Warning Sign Number 2: Occasionally people will develop schedules that contain too much
negative float (being too tight) or too much positive float (being too loose). Either way, it indicates a
problem with the schedule, especially one of realism. Too much negative float indicates that the
schedule cannot be realistically accomplished; too much positive float indicates that estimates for the
tasks are too low.

Task Dependencies and Date Scheduling
A network diagram will show one or more of the following relationships, or dependencies, between tasks.
Finish-to-Start
An earlier activity, or the predecessor, is completed and the next one, the successor, is begun, as illustrated in
Exhibit 8-2. Sometimes the succeeding task is not begun immediately; there is, in other words, a lapse of time
between the end of the predecessor and the start of the successor. That interval is called lag. A task can have
one or more predecessors or successors.




Exhibit 8-1. Network diagram.




Exhibit 8-2. Finish-to-start relationship.
Start-to-Start
Two activities are begun around the same time, as displayed in Exhibit 8-3. Sometimes one task is begun just
a little later than the other; the gap between the start of one task and the beginning of the other is also called
lag.
Finish-to-Finish
Two activities are finished around the same time, as shown in Exhibit 8-4. Sometimes one task will finish
earlier than the other, yet each must finish before its successor is begun. The time between the finish of one
and the other is also called lag.



Exhibit 8-3. Start-to-start relationship.




Exhibit 8-4. Finish-to-finish relationship.
Having identified all the dependencies between the tasks, Perry can apply the time estimates to each task. But
the raw time estimates must be converted to some meaningful value. For starting purposes only, Perry
converts the hour estimates into workdays. He divides the hours by 8 to derive the number of days needed to
complete the task. He then uses this duration, or flow time, to calculate the start and stop date for each task.
Actually, Perry calculates two sets of start and stop dates: early and late start dates, and early and late finish
dates. The early start and early finish dates are the first pair to calculate. The early start date is the earliest
time a task can be begun. The early finish date is the earliest time a task can be completed. These dates are
determined by comparing the duration of a task with the dates for the preceding and succeeding tasks.
Why Some People Don™t Do Scheduling
Occasionally you run into people who do not like schedules. Sometimes that person is even the project
manager.
There are all sorts of reasons for this reluctance. People might feel the time or effort expended to build the
schedule exceeds the value gained. Or they might not want to commit themselves.
If you are working with someone who is reluctant to schedule, you have several options. You can document
a person™s reluctance in a memo and send it to higher-level management. You can hold a group meeting and
cover the schedule in general, letting peer pressure prompt the person to cooperate. A related tactic is to
apply the Delphi method by encouraging input from everyone, then make changes, recirculate for feedback,
and repeat the cycle until everyone is satisfied with the results.

Some dates may not be logically derived from a network diagram. For example, certain tasks may have to
start no earlier than a specific date or may not finish earlier or later than a specific time. In some cases, tasks
may have to begin or finish on a specified date; these are known as constraint dates. Likewise, the start or
finish date of a task may depend on the start or completion of a task in another project. The output of one
project, for example, may feed another. Under these circumstances, the task has an external dependency that
must be considered when calculating start and finish dates.

Perry™s Scheduling Method
Here™s how Perry calculates the early start and early finish dates for his tasks. First, he assigns activity
numbers to the tasks in the WBS and converts the time estimates into flow times, as shown below:


Previous Table of Contents Next




Products | Contact Us | About Us | Privacy | Ad Info | Home

Use of this site is subject to certain Terms & Conditions, Copyright © 1996-2000 EarthWeb Inc. All rights
reserved. Reproduction whole or in part in any form or medium without express written permission of
EarthWeb is prohibited. Read EarthWeb's privacy statement.
Project Management Practitioner's Handbook
by Ralph L. Kleim and Irwin S. Ludin
AMACOM Books
ISBN: 0814403964 Pub Date: 01/01/98

Search this book:
Search Tips

Advanced Search


Previous Table of Contents Next



Activity Number Task Description Hours Duration (Hours/8)
Title
6.1-1.1 3
Identify limousine service to church 24

6.1.1.2 1
Coordinate limousine service to church 8
-----------
6.1.2.1 3
Determine transportation requirements to church 24

6.1.2.2 2
Coordinate transportation to church 16

6.1.2.5 1
Arrange for valet service for church 8

Next, Perry logically ties all the tasks together in a network diagram. (A network diagram was shown in
Exhibit 8-1.) After determining the durations and sequences, Perry calculates the early start and early finish
dates for each task and then the entire project. He performs the forward pass, by moving from the first task in
the network diagram up through the last.
Now, as shown in Exhibit 8-5, Perry knows that task 6.1.1.1 will begin on 8:00 A.M., April 1. He also knows
that the previous task was completed the day before. He knows, too, that the duration is three days, meaning
the task will be done on April 1, 2, and 3, finishing at 5:00 P.M. on the April 3. Task 6.1.2.1 is the successor
and it will begin on April 4 at 8:00 A.M. It, too, has a duration of three days and is completed at 5:00 P.M. on
April 6.
Two successor tasks follow 6.1.2.1. They both will begin on the day after 6.1.2.1 is completed, April 7. Task
6.1.2.2 has a duration of two days, so it is completed at 5:00 P.M. on April 8. Task 6.1.1.2 has a duration of
one day, so its completion date is April 7.




Exhibit 8-5. Forward pass (where ES is early start, EF is early finish).
Task 6.1.2.5 cannot be begun until its two predecessor tasks are finished. The one that is finished the furthest
out”6.1.2.2”must end before 6.1.2.5 can begin. Hence, 6.1.2.5 will begin on April 9 and, with a duration of
one day, will be completed on April 9.
Perry now calculates the late start and late finish dates for each task. Using the same durations and
dependencies in the network diagram, he moves from right to left, beginning with the very last task and
calculating the late start and late finish dates. This movement from right to left is the backward pass, as
shown in Exhibit 8-6.
Assuming that the finish date to task 6.1.2.5 has been set as April 9, Perry can begin the backward pass. He
knows that 6.1.2.5 has a duration of one day and, consequently, begins on that same day, providing a late start
date of April 9. He realizes that task 6.1.2.5 has two predecessors, 6.1.1.2 and 6.1.2.2. Since they each finish
the day before, their late finish dates are April 8. Task 6.1.2.2 has a duration of two days and, consequently,
has a late start date of April 7. Since task 6.1.1.2 is a concurrent activity, and has a shorter duration, it can
begin as far back as April 7, the same late start date as 6.1.2.2. Since 6.1.2.1 is the predecessor to both 6.1.1.2
and 6.1.2.2, it must have a late finish date of April 6. Since task 6.1.2.1™s duration is three days, its late start
date is April 4. And since task 6.1.1.1 is the predecessor of 6.1.2.1, it must finish the day before, on April 3;
with a duration of three days, it must have a late start on April 1.
Is Work Group Participation the Best Way?
In many environments, project managers develop schedules without input or feedback from the people who
will be doing the work. There are several reasons for this.
One is the time required to obtain this input. Getting people involved adds time, and the more people, the
more time to develop the schedule. Also, the project manager has overall responsibility for the project. The
project manager has the big picture perspective and can ensure that “all the pieces fit together.”
The counterargument is that the work group should have a say in building the schedule. Although
participation adds to the flow time, it does offer some powerful advantages. By obtaining input, the project
manager solicits ownership in and commitment to the schedule, especially for the work each person is
responsible to do. Work group participation also helps to raise issues and question assumptions early to
preclude future misunderstandings and problems.




Exhibit 8-6. Backward pass (where LS is late start, LF is late finish).

Note: this is only a partial description of the network diagram for the wedding. It™s a “snapshot” presented here
to illustrate the basics of network diagramming and calculating dates.


The Float
Perry now has four dates for each task: early start, early finish, late start, and late finish. These dates are
necessary to calculate the float for a task. Float is the time an activity can slide without affecting the project
completion date. For instance, if a task does not have to be begun right away, there may be time to slide. Or if
it does not have to be finished as early as possible, there is time to let the date slide a bit.
Perry uses a simple calculation to determine float: the difference between the early start date and the late
finish date, minus the duration, as shown in Exhibit 8-7.


Previous Table of Contents Next
Products | Contact Us | About Us | Privacy | Ad Info | Home

Use of this site is subject to certain Terms & Conditions, Copyright © 1996-2000 EarthWeb Inc. All rights
reserved. Reproduction whole or in part in any form or medium without express written permission of
EarthWeb is prohibited. Read EarthWeb's privacy statement.
Project Management Practitioner's Handbook
by Ralph L. Kleim and Irwin S. Ludin
AMACOM Books
ISBN: 0814403964 Pub Date: 01/01/98

Search this book:
Search Tips

Advanced Search


Previous Table of Contents Next



Tasks given a zero float means that they cannot slide; if they do, then the project end date will slide, too. The
Title
one or more paths through the network diagram that have tasks with zero floats are called the critical path, as
shown in Exhibit 8-7.
There are, in reality, two types of float. The float just described is known as total float and affects the project
end date. The other type is the free float, which occurs on noncritical paths. This is the time that an activity
-----------
can slide without impacting the start date of its successor.




Exhibit 8-7. Critical path showing float.

Other Types of Network Diagrams
Perry has used one type of network diagram, but several other types exist. Perry™s choice is the precedence
diagramming method. It is used most often in nonconstruction applications, such as in the information
systems, pharmaceutical, and engineering industries.
For construction applications, the arrow diagramming method is used. It, too, relies on relationships, but they
take a different form. The arrow diagram uses “nodes” to represent events and arrows to describe the task
between those nodes. Also, this technique uses dummy activities that consume no resources, unlike the
precedence diagramming method.
Another diagramming technique is the bar, or Gantt, chart. The fundamental difference between a bar chart
and a network diagram is that the former does not show dependencies. The bar chart displays a list of tasks
and, for each one, a bar shows the flow time or duration. As Exhibit 8-8 shows, a standard bar chart does not
present all four dates for a task.
The bar chart often is useful, for several reasons. It is easy to read, showing only one set of start and finish
dates. The bar itself provides a visual means to check the status of a task. It is also excellent for “rolling up,”
or summarizing the progress of a related group of tasks. Thus, its simplicity, visual orientation, and
summarization capabilities make it an excellent tool for reporting to senior management. It gives senior
management the big picture rather than the details. A bar chart using roll-ups is shown in Exhibit 8-9.




Exhibit 8-8. Basic bar chart.




Exhibit 8-9. Roll-up bar chart.

The milestone chart is a type of bar chart. It has the outlay of a bar chart but also has an icon or symbol to

<< . .